Eight-mile I-20 repaving in Talladega County could wrap up by year's end

by The Alabama Digestin Main News

Two-lane road with yellow centerline and guardrail beside an I-20 West shield sign, with a forested hill beyond in Alabama.
Photo: formulanone / Wikimedia Commons (CC BY-SA 2.0)

Drivers on I-20 in Talladega County now have new pavement on an eight-mile stretch near Eastaboga, as the state makes its final improvements to a resurfacing job that began in May.

Nearly 46,000 vehicles a day use the six-lane section of interstate, which lies between the Eastaboga interchange at Exit 173 and the overpass at the H.J. Bentley Jr. Parkway.

Crews milled and paved only at night for a few months, and the final asphalt layer is now in place, the Alabama Department of Transportation said in a project update.

Vulcan Materials Asphalt and Construction holds the $6.43 million contract for the resurfacing. It won the job in September 2025 with the lowest bid.

Work has since moved to the ramps and the roadside.

On Tuesday, Nov. 17, crews were painting the ramps at Exit 173. That week, contractors laid permanent lane lines on the exit ramps and put up new guardrails. Guardrail crews were at work on westbound I-20 near Exit 173.

The department said the job could be finished by the end of the year.